Client:

PDR Construction

Project:

Horton Road Demolition & Remediation

Programme Duration:

26 weeks 

Contract Value:

£750k – £1 million 

Works outline:

  • Removal of all licensed & non licensed ACMs identified in R&D survey
  • Full soft strip of all buildings, segregation into designated waste streams and removal to an appropriate waste disposal facility
  • Mechanical demolition of multiple 1,2,3 and 4 storey buildings using DX380 & DX420 excavators with muncher, shear and selector grab attachments
  • Breaking up of all slabs and hardstandings as well as grubbing up foundations
  • Crushing on site to 6f2 grade for reuse
  • Night shifts were completed in order to mitigate disruption to neighbouring properties
  • Extensive asbestos soils remediation